The overall construction works on the US$161 million Soesdyke-Linden Highway are now about 50 percent complete, placing the landmark project at its halfway point. The project is intended to expand the highway and transform it into a modern transport hub.
The upgrade is being carried out through a joint venture between Trinidad-based Namalco Construction Services and local firm GuyAmerica Construction Inc.
According to DPI, Public Works Minister Juan Edghill on Wednesday met with the contractors to review the progress of the project, address challenges, and discuss the way forward.
He urged the contractors to complete the project ahead of its September 4 deadline, noting that major activities are upcoming and the corridor is a vital artery. One such event is the celebration of Guyana’s 60th year of Independence.
“Guyanese from all over the diaspora will be pouring in here. We are working on our tourist product, and I guess by now all contractors understand the thinking of His Excellency, the President, and how we do things,” Minister Edghill said.

“So nationally, things will be taking off, and this corridor is going to be a major corridor,” as he stressed the importance of careful work planning, including bridges, walkways, and road surfaces that can safely accommodate increased use.
Progress varies across the project’s sections. Section one is slightly behind schedule, with about 16.1 kilometers of roadworks still to be completed, while section two is ahead of schedule, with around 90 percent of works executed.
However, rehabilitation works along the vital corridor are 95 percent complete, while reconstruction works stand at approximately 60 percent complete. The current program targets completion of all reconstruction and roadworks by the end of May or into June.
Additionally, contractors are in the process of procuring materials for street lighting, which are expected to arrive by the end of April. Minister Edghill said improved lighting will bring immediate benefits to road users.
“One of the things that is bringing direct benefits to the people in this project is not just the nice surface, riding smooth and nice, but it is the lighting. People want more lighting right now, and in the absence of the markings, the road is very dark at night,” he stated.
Once completed, the upgraded Soesdyke/Linden Highway is expected to significantly improve safety, increase traffic capacity, and support economic growth across Guyana.
Subscribe to get the latest posts sent to your email.
Related News
Revised Local Content Act to include fixed returns for citizens
Secondary school students to be encouraged to form consortiums & pitch business ideas ...
Gov’t plans new transport links to support Palmyra development