GtE Project: No more stalling, pausing or holding up – PM as additional $24.7B approved to advance
Prime Minister (PM) Mark Phillips on Monday justified the Government’s request for an additional $24.7 billion in funding to support activities relating to the Gas to Energy (GtE) Project at Wales, West Bank Demerara (WBD) – which now has a price tag of some US$956 million. During the Committee of Supply, PM Phillips responded to questions from Opposition Member of Parliament (MP) Terrence Campbell about the need for the additional funding, given that billions were already approved for the GtE Project.
“The voted provision was $10 billion. The Honourable Prime Minister came back for another $19 billion, that’s $29 billion. Now he’s coming for another $25 billion, a total of $44 billion over the voted provision of $10 billion. Mr Chairman, this is not budgeted…I would like the Prime Minister to give us a breakdown first of all, for, what caused this request for the extra $25 billion at this point in time,” Campbell asked.
In response, PM Phillips listed costs of some $12.1 billion for Lindsayca, the GtE contractor, as well as roughly $4.25 billion for Siemens Energy for works on the second phase of the development. In light of these revelations, Campbell asked the PM to explain the payment to Siemens Energy, which will manufacture turbines for GtE Phase Two. According to PM, “you don’t go into a store and see a gas turbine on the shelf or in a hangar or in a shop, pay some money, load it up and remove right away, it has to be manufactured”.
“…and you have many requests for similar turbines and we’re in a situation in the world today where the lead time which used to be maybe two years is now extended because there’s an increase in demand for similar turbines and only one set of people manufacturing these turbines in the world…so in order to ensure that we keep within schedule 2030 for Phase Two, we are forced to do long lead procurement, which is we pay up some money upfront and you secure the commitment from the supplier, the rest of money will be paid afterwards,” Phillips explained.
“You have to join the queue earlier, the earlier you can join the queue, is the earlier you can get your turbine and that’s why we were forced to make this decision because we want this project to be handed over to the people of Guyana during this second term,” he added. GtE Phase Two will add 300 megawatts (MW) alongside the first 300 MW combined-cycle power plant at Wales, bringing total planned generating capacity there to 600 MW fueled by natural gas from the Stabroek Block.
The first 300 MW plant is targeting initial commissioning of its first gas turbine by the end of 2026 and full completion in 2027. PM Phillips acknowledged that the project has faced delayed as he justified the need for additional funding to complete this transformative energy initiative. “Yes, we had money budgeted for this year, the money was expended, the project is ongoing, there are costs overrun, we had meetings with the project directors…and coming out of that meeting, in order not to pause this project, may I remind you that we made a promise to the people of Guyana that we will deliver 300 megawatts of electricity at half the cost, we are behind schedule, we don’t wanna go to litigation or anything, we want this project to continue to its end and deliver on our promise to the people and coming out of that meeting, that is why we are asking for the additional money here to take this project to its successful conclusion where we can turn on the power switch and deliver the additional energy to the people of Guyana,” he emphasised.
“This is additional money that we’re asking for because we owe it to the people of Guyana to complete this project, no more stalling, pausing or holding up,” PM Phillips further emphasised. Notwithstanding the delays, he noted that the project remains on schedule for all turbines to be up and running by the end of the first quarter of 2027. Meanwhile, in response to questions from Opposition Parliamentarian Vinceroy Jordan, the PM disclosed that the overall cost for the GtE Project is now US$956 million, up from US$759 million.
“The total of US$200 million additional were requested and we agreed to pay that, to date we paid US$130 million and we have to pay $70 million more. That would take us from US$759 million to US$956 million,” the PM explained. Moreover, in response to questions from MP Campbell, Phillips assured that provisions have been put in place to ensure there are stricter systems in place to limit the need for additional payments. “We have amendment five which was signed by both sides and we have amendment six which is pending and will be signed soon. In effect, what these two amendments are doing is capping but also identifying penalties for any slippage as we go forward. We don’t envision any slippage because we still have a commitment, as signed to in amendment five, that the contractor will complete the project within the given timeframe that is now signed onto by both sides and of course, in an open book manner, we provide money, based on work to be completed towards the completion of this project,” the PM noted.
Further asked if he can assure that there will be no additional requests for funds, the PM said “I’m not clairvoyant but I’m confident that the amendments entered into and the other one soon to be signed will see us to the end of this project with the people of Guyana benefitting from an additional 300 megawatts and they will be paying half of what they’re paying now”.
Meanwhile, the $24.7 billion includes financing for works on the substations, outstanding payments for land acquisition, project management and technical advisory services, and works on the national control centre, among others.